Permitting & Documents
Prysmian’s plans for its Brayton Point manufacturing facility will require local, state and federal approvals. We have an ambitious plan to create a hub for offshore wind energy equipment production. Along the way, we plan to keep the public informed about the project and listen to the Somerset community as we move forward.
FEDERAL
-
Determination of No Hazard to Air Navigation, Notice of Proposed Construction, or Alteration to a Building
FAA DETERMINATION OF NO HAZARD TO AIR NAVIGATION #1
FAA DETERMINATION OF NO HAZARD TO AIR NAVIGATION #2
-
Section 404 Individual Permit, including consultation with the National Oceanic and Atmospheric Administration (NOAA) Fisheries and coordination with the Board of Underwater Archaeological Resources (BUAR) under Section 106
Section 10 of the Rivers and Harbors Act (for work within navigable waters)
Section 103 of the Marine Protection, Research and Sanctuaries Act (to transport dredge material for ocean disposal)
-
National Pollution Discharge Elimination System (for construction sites over one acre)
Permits for construction storm water and dewatering
STATE
-
Review under the Massachusetts Environmental Policy Act
Final Environmental Impact Report (FEIR) - January 3, 2023
Draft Environmental Impact Report (DEIR)
APPENDIX B: ENF Certificate and Comments
APPENDIX C: Transportation Supporting Documentation
APPENDIX D: Marine Fisheries Supporting Documentation
APPENDIX E: Climate Change Supporting Documentation
APPENDIX F: Stormwater Management Supporting Documentation
Final Environmental Impact Report (FEIR) Certificate - February 17, 2023
-
Air Quality Plan Approval Fact Sheet
Permit - Prysmian Limited Plan Approval
Chapter 91 License
401 Water Quality Certification
-
State Register Review
-
CZM Consistency Review
LOCAL
-
-
Planning Board - Definitive Subdivision 10-3-2023
Planning Board - Definitive Subdivision 8-21-2023
Zoning Board - Development Plan Review - 8-17-2023
Zoning Board - Development Plan Review - 7-20-2023
Planning Board - Definitive Subdivision 6-29-2023
Zoning Board - Development Plan Review - 6-22-2023
Zoning Board - Compiled Permit Set - 6-16-2023
Zoning Board - Development Plan Review - 6-15-2023
Planning Board - Development Plan Review 5-23-2023
Zoning Board - Development Plan Review - 5-11-2023
Planning Board - Development Plan Review 4-25-2023
Planning Board - Development Plan Review 3-14-2023
Planning Board - Development Plan Review 1-24-2023
Zoning Board – Development Plan Review 1-19-2023
Zoning Board & Planning Board Site Plan Review
Planning Board - Prelim Subdivision 12-24-2022
Planning Board - Prelim Subdivision 12-20-2022
Prysmian Development Plan Review Project Narrative 12-15-2022
Prysmian Site Plan Set 12-2022
-
DOCUMENTS:
COMPLETED FILINGS/SUBMISSIONS:
LOCAL: Sediment Investigation Report – November 2022
LOCAL: Brayton Point Borings NOI 04-27-2022
LOCAL: Brayton Point Dredge Borings NOI 10-31-2022
LOCAL: Brayton Point Submarine Cable Factory NOI 10-31-2022 (Stormwater Report) (Site Plans)
LOCAL: Subsurface Investigation Report – October 2022
STATE: Prysmian Brayton Point ENF – 05-02-2022
STATE: EJ Screening Form
STATE: Protocolo de Participación Pública de MEPA para Poblaciones de Justicia Ambiental
STATE: Protocolo MEPA de Envolvimento Público para Populações de Justiça Ambiental
STATE: MEPA Draft Environmental Impact Report (DEIR) 08-31-22 (Appendix C) (Appendix F)
STATE: Final Environmental Impact Report (FEIR) 01-03-23 (português) (español)
STATE: FEIR Certificate - 02-17-23
STATE: Final Permit Set 09-21-2023
STATE: Compiled Storm Water Report -September 2023
OTHER DOCUMENTS:
LOCAL: Swansea Community Meeting - July 12, 2023
LOCAL: Brayton Point Sound Study for Board of Health 06-13-2023 (Attachment A)
LOCAL: Somerset Community Meeting 09-13-2022
LOCAL: Presentation to Somerset Board of Selectmen 05-25-2022
STATE: MEPA Virtual Site Visit 05-24-2022
STATE: Final Environmental Impact Report Public Meeting Presentation 2-2-2023